Kleinwabern tram and Wabern renovation approved

Kleinwabern tram project and Wabern centre renovation

The BAV approves the tram extension to Kleinwabern and the renovation of Seftigenstrasse: construction will not begin before 2028, with the appeals phase ongoing.

Context

TL;DR

  • BAV approves the two projects for Wabern
  • Line 9 will be extended to Kleinwabern
  • Construction will start no earlier than 2028
  • The appeals phase is still ongoing

Key facts

  • Projects → «Tram Kleinwabern» and «Sanierung Zentrum Wabern»
  • Decision → October 5, 2026
  • Interchange hub → S-Bahn, buses and trams
  • Affected road → Seftigenstrasse
  • Archaeological excavations → since September 2025

Approval of the two projects

On October 5, 2026, the Federal Office of Transport (BAV) approved the «Tram Kleinwabern» and «Sanierung Zentrum Wabern» projects. The decision concerns the development of transport infrastructure in Wabern and indicates two expected results: better access to public transport for Kleinwabern and greater safety for cyclists and pedestrians.

Line 9 and Seftigenstrasse

The «Tram Kleinwabern» project provides for extending tram line 9 to Kleinwabern. A new public transport hub is planned in the same area, with interchange options between S-Bahn, buses and trams. The text links the project to the growth of the settlement area and speaks of a substantial improvement in public transport service for Kleinwabern.

The «Sanierung Zentrum Wabern» project, on the other hand, concerns the renovation of Seftigenstrasse. The stated objective is to improve conditions for cyclists and pedestrians. The source therefore presents the two projects as complementary: on the one hand, access to the public transport network; on the other, safety conditions along the road.

The first project is centered on the network and the possibilities for transferring between different services. The second is centered on the road and the conditions for those who travel along it by bicycle or on foot. The source keeps these objectives distinct, while placing them within the same BAV decision.

The decision updated the timelines. According to the schedule, work on both projects may begin no earlier than 2028. The appeals phase is still ongoing in the approval procedure.

In addition, archaeological excavations have been underway since September 2025 in the area of the new tram turnaround loop, near the Kleinwabern terminus. The text identifies them as a necessary condition for carrying out the «Tram Kleinwabern» project. For further information on the Seftigenstrasse projects, the source refers to the dedicated website indicated in the notice. Those wishing to follow the section dedicated to public transport can consult the guide to mezzi pubblici.

Operational details

The practical takeaway for travellers

The announcement should be read as two separate interventions, with one point in common: both affect mobility in Wabern. The tram project concerns access to Kleinwabern and transfers between S-Bahn, bus and tram; the road project concerns Seftigenstrasse and the safety of cyclists and pedestrians. However, the joint decision does not make their effects identical: to understand what to follow, each piece of information must be associated with the correct dossier.

Two effects, not one intervention

Table 1: Area
AreaSource's indicationExpected effect
KleinwabernExtension of line 9 and new interchangeBetter access to public transport
SeftigenstrasseRoad rehabilitationImprovement for cyclists and pedestrians
ScheduleWorks for both no earlier than 2028Timeframe indicated by planning
ProcedureAppeals phase ongoingStatus of the authorization procedure

The text measures the expected effect using two practical criteria: access and safety. On the one hand, the planned interchange at Kleinwabern; on the other, the improvement for those travelling along Seftigenstrasse on foot or by bicycle. These are the two reference points to keep in mind when reading updates.

For those looking at the connection with Kleinwabern, the operational detail is the planned possibility of changing between three services at the same interchange. The confirmed point is the new possibility of interchanging between S-Bahn, bus and tram; the text links this interchange to improved access to public transport for Kleinwabern.

The schedule should be read with caution

The time reference is 2028, but the planning refers to a start no earlier than that year. The announcement therefore presents 2028 as the earliest timeframe for work to begin. At the same time, the appeals phase of the authorization procedure is still ongoing. For travel purposes, it is advisable to distinguish the approved project from the actual construction schedule.

The archaeological excavations that began in September 2025 are also a specific element of the tram project. They are located in the area of the new turning loop at the Kleinwabern terminus and are identified as a necessary condition for carrying out the project. The announcement therefore links them directly to the possibility of implementing the project.

To follow updates on the network described in the source, the reference to mezzi pubblici provides a practical starting point.

Recommended tools

For an updated estimate, use the net salary calculator and the CHF-EUR exchange comparator.

Useful tools to protect your net income

To reduce FX leakage, compare CHF-EUR exchange options and banks for cross-border workers.

Key points

What to do now

To follow the progress of the projects in an orderly manner, the reader can follow the steps that can be verified from the communication.

Checklist for following the process

1. Separate the two dossiers. The first is «Tram Kleinwabern»; the second is «Sanierung Zentrum Wabern». This distinction makes it possible to link each update to the correct topic. 2. For the tram dossier, check the references to line 9, the interchange hub between S-Bahn, buses and trams, and the area of the new turning loop near the Kleinwabern terminus. 3. For the road dossier, follow updates relating to Seftigenstrasse and the aim of improving conditions for cyclists and pedestrians. 4. Keep approval and schedule separate. The BAV decision is dated October 5, 2026; the planning indicates that both works will start no earlier than 2028, and the appeals phase is still ongoing. 5. Use the Seftigenstrasse project website indicated in the communication as a reference for further information.

How to interpret upcoming communications

The information to look for in updates is not merely confirmation of the approval, which has already arrived, but the possible evolution of the procedure and timelines. The source indicates, in fact, that the plans were updated after the decision and that the proceedings have not yet moved beyond the appeals phase. For this reason, it is advisable to maintain the distinction between 2028, indicated as the earliest possible start date, and the appeals phase still in progress.

The archaeological excavations should also be considered precisely. They began in September 2025 in the area of the new tram turning loop, near the Kleinwabern terminus, and constitute a condition for implementing the «Tram Kleinwabern» project. The reader can therefore consider them part of the implementation procedure, without turning their presence into a prediction about the start of the works.

The communication also links the two projects to concrete needs: better access to public transport for Kleinwabern and greater safety for bicycles and pedestrians. When consulting updates, it is advisable to check which of the two needs each piece of information refers to, avoiding confusing the S-Bahn-bus-tram hub with the renovation of Seftigenstrasse.

To organize consultation of the services involved, use the guide to mezzi pubblici.

Evaluating a Ticino job offer? Simulate your net payslip: enter gross salary, marital status and municipality for a detailed breakdown.

Source: be.ch

First day as a cross-border worker? Our practical guide walks you from cantonal registration to your first paycheck.

Frequently Asked Questions
Who approved Wabern's projects?
The approval was granted by the Federal Office of Transport (BAV) in a decision dated October 5, 2026. It concerns «Tram Kleinwabern» and «Sanierung Zentrum Wabern». The source links the approval to the development of transport infrastructure in Wabern, improved access from Kleinwabern to public transport, and greater safety for cyclists and pedestrians.
What does the Tram Kleinwabern project entail?
Line 9 will be extended to Kleinwabern. A new public transport hub is planned at the location, with interchange options between S-Bahn, buses and trams. According to the source, this will substantially improve access to public transport for the growing settlement area. The hub is part of the «Tram Kleinwabern» project approved by the BAV.
When will the work begin?
According to the planning updated following the decision of October 5, 2026, the start of construction for both projects is scheduled no earlier than 2028. The appeal phase in the authorization procedure is still ongoing. The source therefore presents 2028 as the earliest date in the schedule, without indicating a precise day for the opening of the construction sites.
Why are archaeological excavations underway in Kleinwabern?
Archaeological excavations have been taking place since September 2025 in the area of the new tram turnaround loop, near the Kleinwabern terminus. The source identifies them as a necessary condition for constructing “Tram Kleinwabern,” thus linking them directly to the project approved by BAV.