Node of Biasca: the last phase of work from 31 August (cross-border guide)

Work at the Biasca interchange node: the last phase begins on 31 August 2026 and ends on 12 September, with impacts on traffic and alternate senses.
Context
In a nutshell
- Last phase of Biasca node work: from 31 August to 12 September 2026
- Daytime work from August 17 to September 4 (07:00-17:30)
- Laying of the sound-absorbing night wear layer from 7 to 12 September
- Alternately regulated traffic in the night bands
Key facts
- What: Arrangement of the Biasca interchange node
- When: From 17 August 2026 to 12 September 2026
- Where: Biasca SBB station area, via Bellinzona, via Gen. Guisan and Via A. Giovannini
- Who: Department of the Territory (DT) and Municipality of Biasca
- Amount: Not yet specified
The Department of the Territory (DT) and the Municipality of Biasca have announced the start of the last phase of work for the arrangement of the Biasca interchange node, located in the SBB station area. The road maintenance and redevelopment operations will enter the last phase starting on Monday, August 31, 2026, with a conclusion scheduled for September 12, 2026.
Operational planning details
The work schedule is divided into three main moments. From Monday 17 August 2026 to Friday 4 September 2026, the activities will take place during the day, specifically from 07.00 to 17.30. During the first two weeks of this period, the workers will proceed to lay the wear layer on the yards in front of the SBB station. In the third week, the focus will shift to Via Bellinzona, where the preparatory work for the
Operational details
Implications for cross-border commuting
For border crossers who transit daily through Biasca, these road maintenance operations represent a critical element for travel times. Although the cantonal road section remains regularly open to traffic during the day, the road closures on Via Bellinzona between 17 August and 4 September 2026 can generate queues and slowdowns.
The risk of congestion is particularly high during the morning and late afternoon rush hours, when the flow of vehicles to Bellinzona or border crossings is at its peak. It is advisable for those who work in Ticino and reside in Italy to carefully monitor the site signs and follow the instructions of the traffic control agents to avoid unforeseen obstacles.
Analysis of transit scenarios
We can analyze two main scenarios for those who have to cross the Biasca works area in the indicated period:
1. Daytime scenario : Between 17 August and 4 September, transit is guaranteed, but with possible slowdowns due to punctual shrinkage. The border worker travelling between 07:00 and 17:30 must allow extra time for the commute.
2. Night Scenario: From September 7 to 12, traffic will be regulated in an alternate direction on a single lane of travel by regulators. This scenario
Recommended tools
For an updated estimate, use the net salary calculator and the CHF-EUR exchange comparator.
Key points
Practical guide to driving in the construction site area
To navigate the Biasca area properly between 17 August and 12 September 2026, drivers must follow a specific safety and traffic procedure. Here are the recommended steps for managing day-to-day:
- Checking the calendar: Make sure that the transit day falls between the critical dates (17 August - 4 September for day jobs; 7-12 September for night alternate directions).
- Attention to signs: Carefully follow the temporary site signs, which may vary depending on the phase of the work.
- Attention to the agents: Give absolute priority to the indications of the agents in charge of regulating traffic, which take precedence over signs.
- Caution in crossing: Take the utmost care when crossing the work area to protect your safety and that of the site personnel.
# Border commuter tools
In addition to managing travel times in Biasca, those who work in Switzerland must properly manage their tax and social security position. For those who have doubts about their paycheck or the deductions made by the employer, it is essential to use accurate simulation tools.
If you would like to calculate your net salary in Ticino, please use our calcolatore fiscale to get an accurate estimate of taxes at source and withholdings
Source: ticinonews.ch
Frequently Asked Questions
- When do the works at the Biasca node end?
- The works for the arrangement of the Biasca interchange node will officially end on 12 September 2026, after the last phase of laying the sound-absorbing wear layer and the interventions on the roundabouts of Via Gen. Guisan and Via A. Giovannini.
- Will traffic be blocked during the day?
- No, during the day the section of cantonal road in question will remain regularly open to traffic. However, between 17 August and 4 September 2026, there may be occasional narrowing of the carriageway on Via Bellinzona.
- Is access to public transport and relief guaranteed on average?
- Yes, for the entire duration of the works, the authorities have confirmed that access to the public transport stops by road and to the area in front of the SBB station will always be guaranteed, as well as the transit of rescue vehicles.
Related articles
- Svincolo A2 Biasca: rischi e impatti per frontalieri
- Lavori sul nodo ferroviario di Seveso: stop ai treni della S4 tra Seveso e Camnago dal 3 al 23 agosto
- Permessi di lavoro in Ticino: dal 3 agosto la domanda è online
- Littering, lavoro e aviazione: le novità del 1° agosto
- Da Biasca all'Ucraina: sei volontari in missione umanitaria