Albate-Molteno railway electrification: Como-Lecco halt

Construction work to begin in mid-December for the electrification of Albate-Molteno; traffic suspended on Como-Lecco until June 2029. Investment of 170 million euros.
Context
TL;DR
- Construction work scheduled for mid-December on the Albate-Molteno line
- Como-Lecco traffic suspended at least until June 2029
- Estimated investment for the project: approximately 170 million euros
- Another 44 million is still needed for Molteno-Lecco
Key facts
- Intervention → electrification of the Albate-Molteno line
- Construction work → start in mid-December
- Suspension → Como-Lecco until at least June 2029
- Investment → approximately 170 million euros
- Expected outcome → 34 and 68 services; TILO to Switzerland as far as Lecco
Construction work on the electrification of the railway line between Albate and Molteno is scheduled to begin in mid-December. The project will be discussed on Friday, October 9, at Lariofiere, during the meeting of the Competitiveness Roundtable. The start of the work was confirmed by senior officials of Rete Ferroviaria Italiana at a hearing of the Regional Council.
For those who use the connection between Como and Lecco, the consequence already indicated is a total suspension of rail traffic until at least June 2029. Details of the replacement bus services remain to be defined. The source therefore does not provide timetables, stops or alternative routes to be used during the closure.
A project divided into two lots
The project strategy aims to avoid work on road overpasses and underpasses, so as not to affect local traffic. The construction areas will be located near major roads. For the second lot, between Molteno and Lecco, the technical-economic feasibility study has been completed and the environmental impact assessment procedure has been initiated with the Ministry. An electrical substation is also planned in the La Piccola area of Lecco.
The total estimated investment for the project is approximately 170 million euros. The Regional Department for Infrastructure intends to propose that the second section be funded by the Ministry under the new program contract with RFI. Completion of the Molteno-Lecco section will require approximately two years and four months of construction work, but 44 million still need to be secured and the authorization process completed first.
The final plan provides for more services and the definitive abandonment of diesel-powered trains: Albate-Molteno would increase from 24 to 34 trains per day, and Molteno-Lecco from 46 to 68. Electrification would also allow TILO services to Switzerland to be extended as far as Lecco and would provide an alternative route for freight trains coming from Swiss territory. Requests to upgrade the stations, put forward by the Chamber of Commerce and reiterated by the Province of Lecco in its environmental comments, remain open.
Operational details
For travelers: two very different phases
For a cross-border commuter who uses the rail connection between Como and Lecco or looks to the future extension of trains toward Switzerland, the project has two distinct effects: a long interruption during the works and a broader service after electrification. The source makes it possible to clearly define the first and second outcomes, but not to establish how each day's travel will be organized.
Before, during and after
| Phase | Available data | Cautious interpretation |
|---|---|---|
| Before the upgrade | 24 trains per day between Albate and Molteno; 46 services between Molteno and Lecco | These are the values from which the announced increase starts |
| During the construction works | Complete suspension of Como-Lecco traffic until at least June 2029; replacement buses still to be defined | The source does not allow a detailed replacement service to be scheduled |
| After electrification | 34 and 68 services; end of diesel trains; TILO to Switzerland as far as Lecco | The expected result is a broader rail service |
The distinction is crucial for a cross-border commuter who must interpret the news without confusing the construction phase with the service planned after electrification. The increase from 24 to 34 and from 46 to 68 does not describe the services available during the suspension: it indicates the announced upgrade for the subsequent phase.
Likewise, the extension of TILO connections toward Switzerland as far as Lecco is presented as an effect of electrification. The source does not indicate an activation date, timetables or stops for this service; it is therefore not possible to turn the announcement into a precise schedule.
For those who work across the border and travel in the affected area, the certain fact is the railway suspension. The replacement service, on the other hand, has not yet been described in detail. The goal of avoiding work on overpasses and underpasses also offers only a limited indication: the design aims to reduce the impact on local roads, but the source does not quantify any road travel times or travel savings.
The benefit for freight trains coming from Switzerland must also be kept separate from passenger service. The alternative route is intended for freight traffic, while the increase in services and the TILO extension concern the rail connections indicated for passengers.
Useful planning tools
To estimate your pension strategy, use the pension planner and the pillar 3 simulator.
Useful planning tools
To estimate your pension strategy, use the pension planner and the pillar 3 simulator.
Key points
Practical steps for reading the news
The source makes it possible to construct an operational sequence, but not a booking procedure or a bus timetable. For a cross-border commuter interested in the Como-Lecco connection, it is therefore advisable to distinguish the data already indicated from the decisions still open.
1. Establish the first time reference. Consider mid-December as the start of the works indicated in the source. Keep this date separate from the line closure: Como-Lecco traffic is expected to be completely suspended until at least June 2029, with no more precise end date in the text.
2. Separate the two lots. Albate-Molteno is the section affected by the start of the works, while Molteno-Lecco is the second lot. For the latter, the technical-economic feasibility study has been completed and the environmental impact assessment procedure has been initiated at the Ministry. 44 million euros still need to be secured and the authorization process completed; the estimated duration of the construction site is approximately two years and four months.
3. Do not anticipate the bus service. The source says that the details of the replacement services have yet to be defined. Therefore, do not assign a route, stop or timetable not indicated to the rail replacement service.
4. Distinguish the temporary phase from the final result. The suspension concerns the works; after electrification, 34 daily services are planned between Albate and Molteno and 68 between Molteno and Lecco, with the abandonment of diesel trains and the extension of TILO services toward Switzerland as far as Lecco.
5. Keep the points still open separate: funding for the second section must be proposed in the new program agreement with RFI, and the requests to upgrade the stations mentioned by the Province of Lecco remain on the table.
The scope of the information
For a cross-border commuter seeking updates on the G permit, AVS, LPP, LAMal, tax rebates, withholding tax or double taxation, this source provides no data: its subject is railway infrastructure and the organization of services during and after the works. Therefore, do not attribute tax or social-security effects to this project, because they are not described in the text.
To orient yourself regarding the transport services mentioned, consult mezzi pubblici Ticino.
Discover Ticino job offers updated daily: 4,000+ positions from Swiss companies hiring cross-border workers.
Source: comozero.it
Frequently Asked Questions
- When will the works begin and for how long will the Como-Lecco line be suspended?
- The start of construction works for the electrification of the railway line between Albate and Molteno is scheduled for mid-December. For those using the connection between Como and Lecco, a complete suspension of rail traffic is planned until at least June 2029. Details of the replacement bus services remain to be defined, and no timetables, stops, or alternative routes have been provided.
- What is the total investment and what benefits are expected after electrification?
- The total estimated investment for the project is approximately 170 million euros. After electrification, Albate-Molteno would increase from 24 to 34 trains per day, while Molteno-Lecco would increase from 46 to 68. Electrification would also enable TILO services toward Switzerland to be extended as far as Lecco and the definitive abandonment of diesel trains.
- How is the project between Albate-Molteno and Molteno-Lecco being managed, and what issues remain open?
- The project is divided into two lots. For Albate-Molteno, construction works begin in mid-December. For the second lot, between Molteno and Lecco, the technical and economic feasibility study has been completed and the environmental impact assessment procedure has been initiated at the Ministry. This section is still short of 44 million euros, and the authorization process must be completed. The Regional Department for Infrastructure intends to propose funding in the new program contract with RFI.
- Does the project also cover services for cross-border commuters traveling to Switzerland?
- Yes, electrification provides for the extension of TILO connections toward Switzerland as far as Lecco, offering a broader travel option for passengers. In addition, the project will provide an alternative route for freight trains coming from Swiss territory. No tax or social security effects related to this project are indicated.
Related articles
- All articles: Salaries
- Elettrificazione Albate-Molteno: lavori da dicembre 2024
- Navigazione Lago di Lugano: stagione 2026 al via
- Como e Lecco: rischio perdita 14mila lavoratori entro 2029
- Trenord potenzia Como-Milano: 4 treni in più per i frontalieri
- Riapre il Circolo ad Albate: una piazza al coperto per la comunità